Table 12-4 The following represents a project with known activity times. All times are in weeks. Table 12-4 The following represents a project with known activity times. All times are in weeks.   -Using the data in Table 12-4, determine the latest time activity A can be started without delaying the project completion. A)  4 B)  3 C)  8 D)  6 E)  None of the above -Using the data in Table 12-4, determine the latest time activity A can be started without delaying the project completion.


A) 4
B) 3
C) 8
D) 6
E) None of the above

F) C) and D)
G) A) and E)

Correct Answer

verifed

verified

Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks. What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)


A) 0.68
B) 0.78
C) 0.22
D) 0.32
E) None of the above

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

The variance of the project completion time is equal to the sum of the variances of all the activities.

A) True
B) False

Correct Answer

verifed

verified

Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 14, and 18 days respectively, compute the PERT expected activity time for this activity.


A) 14
B) 12
C) 11
D) 13
E) None of the above

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

The first step in planning and scheduling a project is to develop the ________.


A) employee scheduling plan
B) PERT/CPM network diagram
C) critical path
D) work breakdown structure
E) variance calculations for each activity

F) B) and D)
G) A) and C)

Correct Answer

verifed

verified

Table 12-4 The following represents a project with known activity times. All times are in weeks. Table 12-4 The following represents a project with known activity times. All times are in weeks.   -Using the data in Table 12-4, what is the latest possible time that C may be started without delaying completion of the project? A)  0 B)  4 C)  8 D)  10 E)  None of the above -Using the data in Table 12-4, what is the latest possible time that C may be started without delaying completion of the project?


A) 0
B) 4
C) 8
D) 10
E) None of the above

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

The process of smoothing out the utilization of resources in a project is called


A) CPM.
B) PERT.
C) project crashing.
D) work breakdown structure.
E) resource leveling.

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

The project described by: The project described by:   has a critical path of length of ________. A)  21 days B)  14 days C)  23 days D)  32 days E)  None of the above has a critical path of length of ________.


A) 21 days
B) 14 days
C) 23 days
D) 32 days
E) None of the above

F) None of the above
G) All of the above

Correct Answer

verifed

verified

In PERT analysis, the probability of the optimistic time occurring should be on the order of ________.


A) 1/2
B) 1/3
C) 1/6
D) 1/10
E) 1/100

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

With CPM, we are able to calculate the probability of finishing the project within a specified time.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a concept associated with CPM?


A) normal time
B) probability
C) normal cost
D) crash cost
E) deterministic network

F) C) and D)
G) A) and D)

Correct Answer

verifed

verified

Given the following small project, the critical path is ________ days. Given the following small project, the critical path is ________ days.   A)  10 B)  14 C)  16 D)  20 E)  None of the above


A) 10
B) 14
C) 16
D) 20
E) None of the above

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

PERT stands for ________.


A) probabilistic evaluation and review technique
B) program evaluation and review technique
C) probability of expected run times
D) program of expected run times
E) project evaluation and review technique

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

PERT assumes that the total completion time of a projects follows which of the following probability distributions?


A) normal
B) exponential
C) binomial
D) Poisson
E) None of the above

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

The first step in planning and scheduling a project is to develop the work breakdown structure.

A) True
B) False

Correct Answer

verifed

verified

Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days respectively, compute the expected time for this activity.


A) 3
B) 4
C) 5
D) 6
E) None of the above

F) B) and D)
G) C) and D)

Correct Answer

verifed

verified

In PERT, the most likely completion time of an activity is used to represent that activity's time within a project.

A) True
B) False

Correct Answer

verifed

verified

Given an activity's optimistic, most likely, and pessimistic time estimates of 1, 9, and 23 days respectively, compute the PERT expected activity time for this activity.


A) 10
B) 12
C) 9
D) 11
E) None of the above

F) D) and E)
G) A) and B)

Correct Answer

verifed

verified

Through the use of PERT/CPM, astute managers can derive flexibility by identifying noncritical activities and replanning, rescheduling, and reallocating resources such as personnel and finances.

A) True
B) False

Correct Answer

verifed

verified

The critical path of a network is the


A) shortest time path through the network.
B) path with the fewest activities.
C) path with the most activities.
D) longest time path through the network.
E) None of the above

F) A) and C)
G) D) and E)

Correct Answer

verifed

verified